Institute for Brick and Tile Research
Batch Kiln

In August 2020, the kiln's walls were coated with Emisshield Ceramic fiber coating, resulting in a 6% reduction in gas consumption.

Celsa Nordic

Pusher Furnace

“The weighted average we have got as a result of our analysis is 5.55% improvement in the post-coating period compared to the pre-coating period.”

Bremerhaven

Roller Kiln

In July 2022 walls and ceiling were coated with an increased production of 4% and energy savings of 6%.

Ziegelwerk Bellenberg
-
Tunnel Kiln

Emisshield® was able to provide increased uniformity in heat distribution and after optimization of the kiln energy savings of 6% were sustainably documented.

Dachziegelwerke

Tunnel Kiln

Applied in February 2022. Flue gas was reduced. Burner settings were adjusted (gas reduced). Currently an overall savings of about 6% in energy consumption were achieved.

CREATON Produktions GmbH 

Tunnel Kiln

Together with Cress, Creaton revised all kiln data and recognized that exhaust temperature increased up to 50°C. Current energy savings are reported between 3,5% and 6% depending on format

Walther Dachziegel

Tunnel Kiln

Due to better temperature distribution in the furnace, the next to the bottom cassettes on the kiln car could be loaded again with roof tiles which gave an 8% increase in production.

Ziegelwerk Klaus Huber

Tunnel Kiln

Flue gas draught has been reduced by approx. 50%, burners operate with less gas pressure, flue gas temperature is currently still too high and ceiling is too hot outside.

Scherm­afbeelding 2026-02-06 om 11.33.16.png

FRISA steel
Batch reheat furnace

The combined overall furnace energy savings and production increase was

approximately 20%.

Scherm­afbeelding 2026-02-06 om 11.48.21.png

 Ladle Pre-Heater 

11.5% reduction in fuel consumption for a 40-hour schedule when both the barrel and working lining were replaced. 

Scherm­afbeelding 2026-02-06 om 12.11.09.png

Swarf Door

By applying Emisshield to the ceramic fiber of the Swarf Door, the plant was able to extend the life of the door to ten weeks of production, an increase of about 3X.

Scherm­afbeelding 2026-02-06 om 12.23.56.png

Engels baksteen

Tunnel Kiln

Emisshield® was able to provide increased uniformity in heat distribution and energy savings of 3,1% were sustainably documented. The gas consumption for 2024 includes the startup phase and recipe adjustments. 

Scherm­afbeelding 2026-02-11 om 12.09.49.png

Vedanta Aluminium

Melting holding

Heat loss reduction: there was a saving of 12°C temperature increase in the

hot metal temperature in the Emisshield coated furnace#2 along with the 9.3

MT higher metal charge compared to the uncoated Furnace#1.

Scherm­afbeelding 2026-02-11 om 12.18.41.png

Novelis Korea

Pusher Furnace

8-10% energy savings

The heat-up time was improved by 6 hours to bring the ingots to 600°C. Temperature of the outside walls and exterior decreased an average of 25°C, measured by a thermograph at regular intervals.